PILE FOUNDATIONS
Name of Work : Construction of Pilling works at Kandla Pump Station, Kandla.
 
Client : Indian Oil Corporation Ltd., (Pipe Line Dn), Kandla.
 
Cost of Work : Rs. 3.82 Millions
 
Year of Completion : December 1999
 
Description of Work : 12 Nos. of Piles each of 800 mm Dia and Length 20 M, Pile Cap (2 nos.)
 
 
Construction of Pilling works at Kandla Pump Station, Kandla.
 
Construction of Pilling works at Kandla Pump Station, Kandla.
     
Excavation of Pile Cap in action (all safety measures have taken considering surrounding running plant)
  Pile Foundation for Booster Pump House (besides running pumps) at I.O.C.L. Plant, Kandla
 
 
Remarks : The foundation for Booster was to be provided in the existing Structures and close to running Plant and Machinery. The bottom of Pile Cap, being 4.5 M below Floor Level, the excavation in collapsible slushy soil posed a number of problems in retaining earth and safe guarding the existing structures. But this problem was overcome by deploying adequate shoring and shuttering and speedy execution of the work by us.