PILE FOUNDATIONS
Name of Work : Protective measures for GAS Pipeline across MAHI River at DABKA-GAJNA section.
 
Client : Engineer In-charge Gas Authority of India Ltd., BARODA
 
Cost of Work : Rs. 2 Millions
 
Year of Completion : July 1993
 
Description of Work : Protective measures for GAS Pipeline across MAHI River at DABKA-GAJNA section.
 
 
Protective measures for GAS Pipeline across MAHI River at DABKA-GAJNA section.
Protective measures for GAS Pipeline across MAHI River at DABKA-GAJNA section.
 
 
Remarks :
  • GAIL's 2 numbers Gas Pipe Line across River Mahi was exposed due to scouring in floods and were on the verge of scrapping. GAIL had entrusted us to do the Protective on emergency basis. The same were carried out by us by constructing Concrete Anchors with Bored Cast-in- Situ Pile foundation and from these, Pipe were restrained from movement by tying steel core wire rope with and in-hously design clamping system, approved by GAIL’s Consultant WAPCOS New Delhi.