CONTINUOUS CONCRETE DIAPHRAGM WALLING
Name of Work : Construction of Diaphragm wall for Causeway cum weir Project across RIVER TAPTI near SURAT.
 
Client : General Manager ECC Construction Group C/o. L & T
 
Cost of Work : Rs. 4 Millions (excl. cost of material)
 
Year of Completion : March 1995
 
Description of Work : Construction of R.C.C diaphragm wall 480 meters long having 60 cm width (Total 2500 sq.m), for Causeway cum weir project across River Tapti near SURAT.
 
 
Construction of Diaphragm wall for Causeway cum weir Project across RIVER TAPTI near SURAT.
 
 
Remarks :
  • Prestigious project of Diaphragm wall for ECC has been carried out with the help of Kelly-mounted Grab attached with TATA 320 crane with great success.