BRIDGES & FLYOVERS
Name of Work : Construction of Road Over Bridge near Sabarmati Railway Station
 
Client : The C. E. (Const.) Western Railway, Ahmedabad.
 
Cost of Work : Rs. 28.2 Millions
 
Year of Completion : June 1994
 
Description of Work :

The 147 meter long R.O.B is having total 5 spans including 3 open foundation ( 4 x 3 = 12 total ). and 3 Pile foundation of 750 mm diameter ( 4 x 4 x 3 = 48 total ). Depth of piling was 22 to 24 meter deep, R.C.C. square column as sub-structure and 40 meter x 2, 27.805 meter long P.S.C Girders and 19.597 meter & 19.598 meter long R.C.C Girders with R.C.C slab, as Super structure.

 
 
Construction of Road Over Bridge near Sabarmati Railway Station
Construction of Road Over Bridge near Sabarmati Railway Station
 
Construction of 40 meters long PSC girder in
action for R.O.B at Sabarmati
Chimanbhai Patel R.O.B. at Sabarmati
(Ahmedabad)
 
 
Remarks : This project was completed 3 days ahead of original Time Limit. Some of the projects highlights along with other challenging activities were :
  • The entire work was carried out in " Running Train " conditions.

  • The Pre-stressed girders over electrified lines were cast 2.1 meter over the pedestal level and then side shifted up to 5.6 meter & lowered in the permanent position.