BRIDGES & FLYOVERS
 
Name of Work : Design and construction of New BG Railway Bridge on river SIRI near Nadiad
 
Client : The C. E. (Const.) Western Railway, Ahmedabad.
 
Cost of Work : Rs. 12 Millions
 
Year of Completion : December 1992
 
Description of Work :

Design and construction of New Broad Gauge Railway Bridge no.11 ( New no.40 ) length 131.82 meter (5 x 19.12 meters + 2.18 meters ) Pre-stressed Concrete Girder across River SIRI at Km. 6.55 including foundations consists of thousand mm diameter Bored Cast-in-Situ Pile(Total 42 no. 22 meter deep) solid R.C.C. pier as Sub-structure and PSC Girder and R.C.C. deck Slab as Super-structure, along with earth work around at behind the abutment in connection with the conversion of NADIAD/KAPADVANJ MG LINE in to BG and extension up to MODASA.

 
 
Design and construction of New BG Railway Bridge on river SIRI near Nadiad
 
New BG Railway Bridge across River Siri at Nadiad.
 
 
Remarks :
  • All 14 Precast Prestressed Girder were Cast-in period of 5 months including monsoon period.

  • Special launching trusses spanning from pier cap were fabricated and use for the Gorge portion during monsoon period