BRIDGES & FLYOVERS
Name of Work : Construction of bridge across river Ambika, Flyover at Gandeva, Flyover at Alipore and ROB at Bilimora on Surat Dahisar section.
 
Client : Modern Road Makers Pvt. Ltd., (IRB), Mumbai.
 
Cost of Work : Rs.184.8 Million (excluding cost of material)
 
Year of Completion : August 2011
 
Description of Work :

Ambika River Bridge:

(Length :236 m, Width: 12 m)

Foundation :

1200 mm dia    (depth 22 to 25 m)

Substructure :

RCC

Superstructure :

5 x 42.06 + 2 x 13 m :  PSC I Beam / Solid slab

Gandeva Flyover:

(Length :190 m, Width: 12.075 m)

Foundation :

1000 mm dia (30 m depth)

Substructure :

RCC

Superstructure :

6 x 31.6 m : PSC I Beam

Alipore Flyover:

(Length :318 m, Width: 12.075 m)

Foundation :

Open Foundation

Substructure :

RCC

Superstructure :

10 x 31.8 m : PSC I Beam

Bilimora ROB:

(Length :191 m, Width: 12.075 m)

Foundation :

1200 mm dia piles (31 m depth)

Substructure :

RCC

Superstructure :

6 x 31.8 m : PSC I Beam

 
 
Ambika River Bridge Ambika River Bridge
 
Ambika River Bridge
   
Alipore Flyover Bridge Alipore Flyover Bridge
 
Alipore Flyover Bridge
   
Gandeva Flyover Bridge  
   

Gandeva Flyover Bridge