BRIDGES & FLYOVERS
Name of Work : Construction of 2 - two lane Flyover bridge on 60 m wide Surat - Bardoli Road at Aai Mata junction for BRTS under JuNURM Scheme, Surat.
 
Client : Surat Municipal Corporation, Surat.
 
Cost of Work : Rs.326 Millions.
 
Year of Completion : January 2011
 
Description of Work :

Foundation :

1200 mm dia piles

Substructure :

RCC Pier and Pier Cap

Superstructure :

2 x 45 m PSC Box + 18 x 20 m PSC I Girder (Pretensioned)

Approaches :

R.E.structure.

 
 
Conventional Routine Load Test on Pile Pier and Pier Cap
 
Conventional Routine Load Test on Pile
Pier and Pier Cap
 
Casting of Precast Pretensioned I Girder at casting yard Prestressing of Precast I Girder at casting yard
 
Casting of Precast Pretensioned I Girder
at casting yard
Prestressing of Precast I Girder at
casting yard
   
Lifting and launching of Precast Pretensioned I Girder in position using two Crawler Cranes Lifting and launching of Precast Pretensioned I Girder in position using two Crawler Cranes
 
Lifting and launching of Precast Pretensioned I Girder in position using two Crawler Cranes
   
Casting of PSC Box Girder Erection of RE Panel
   
Casting of PSC Box Girder Erection of RE Panel
   
 
 
Remarks :
  • The foundation of RCC bored piles (about 20 m long) were executed using MAIT HR 180 Hydraulic Rig. 144 nos. of Pretensioned Precast I Girders were cast in casting bed and launched them in position with the help of Crane. The 45 m box girders were cast in situ.