BRIDGES & FLYOVERS
Name of Work : Construction of Railway Over Bridge (ROB) in lieu LC No. 3C on Surat – Bhusaval main line and Bhestan – Bhusaval loop line joining Dindoli and Godadara area on 45 m wide T.P. / D. P. road at Surat.
 
Client : Surat Municipal Corporation
 
Cost of Work : Rs.301.7 Million.
 
Year of Completion : Work in Progress
 
Description of Work :

Foundation :

1000 mm dia piles

Substructure :

RCC

Superstructure :

PSC / composite steel girders
19 span of 20.1 to 36.38 m PSC girders
2 spans of 24 and 30 m composite steel girder over Railway track.

Approaches :

Reinforced Earth Structure