Name of Work
: |
Design & Construction of
two lane bridge across river Mahi its approaches
near Vasad from km 91/5 to 93/0 and its merging
in A’bad-Baroda sections of NH No. 8
(Under BOT Scheme) (in JV). |
|
Client : |
National Highway Circle, Vadodara. Government
of Gujarat |
|
Cost of Work : |
Rs. 420.00 Millions |
|
Year of Completion : |
April 2000 |
|
|
Description of Work : |
Design and construction of high level bridge
(1500 Meters including approaches) under BOT
Scheme ( In J.V with Rajkamal Builders ) was
consisting of :
Foundation : Well foundation ( 7 m
dia. ) 35 m deep
Substructure : RCC circular Pier ( 3 m
dia)
Superstructure : PSC girders ( 16 x
33.53 + 2 x 14.26 m) and RCC deck slab
Approaches : Earthen Bank and Road
|
|
|
|
|
|
|
|
|
|
|
Road work in action |
|
Road
work in action |
|
|
|
|
|
|
|
|
|
View of a Bridge across
river Mahi on B.O.T. |
|
View
of a Toll Plaza Equipped with 5 Booths
and 4 Lanes in each directions. |
|
|
|
|
|
|
|
|
|
The Project Entrepreneur
VIJAY MISTRY CONSTRUCTION AND RAJKAMAL
BUILDERS PVT. LTD. |
|
Mahi
B.O.T. Project |
|
|
|
|
|
|
|
|
|
Well Foundations (
7 meter dia., 35 meter deep ) in action |
|
Super
structure ( PSC GIRDERS ) in action |
|
|
|
|
Remarks
: |
- Design and planning of the bridge meticulously
done as per M.O.S.T standard and got approved
in a short period of 2 months, 14 nos. of
well foundations were completed in a period
of 6 ½ months time during that lot
of artisan conditions were found. To achieve
the planned fast track schedules numbers of
resources were mobilised such as 8 nos. of mobile
crane were deployed for various activities of
material handling, well sinking, sophisticated
staging and shuttering of materials, all requires
construction materials were arranged timely
to match the planned productivity at site.
- PSC and RCC work of substructure and superstructure
were carried out with in housely developed shuttering
and staging. Prefabricated RCC slab panels
were used as shuttering for casting , deck slabs
to get superior finish and save time of construction.
- All precautions and measures have been taken
to ensure quality control as per M.O.S.T
standards and specifications.
- It is planned to put toll plaza with required
lan configuration along with latest sophisticated
computerized toll collection system for
better convenience of users. (Work has
been completed in a period of 15 months against
allotted time period of 24 months.)
|
|