HARBOUR WORKS - WHARVES, JETTIES, BERTHS & DOLPHINS
Name of Work : Strengthening of Cargo Berth No. 1 - 5 at Kandla Port Trust (Damaged by Earthquake) - Providing additional row of piles
 
Client : Kandla Port Trust, Kandla
 
Cost of Work : Rs. 159.9 Millions
 
Year of Completion : July 2003
 
 

 
Name of Work : Strengthening of the existing fisheries jetty for Salt Export at Jakhau, Kutch
 
Client : Goodearth Maritime Ltd., Chennai - 600 017
 
Cost of Work : Rs. 18.53 Millions
 
Year of Completion : August 2001
 
 

 
Name of Work : Restoration of Maintenance Jetty (damaged during cyclone) at Kandla - Providing alternate approach
Restoration of Maintenance Jetty (damaged during cyclone) at Kandla - Providing alternate approach
 
Client : Kandla Port Trust, Kandla
 
Cost of Work : Rs. 19.2 Millions
 
Year of Completion : July 2001
 
 

 
Name of Work : Widening the berthing Jetty for additional transit area at port Magdalla
 
Client : The C. E. O. & V. C. (G. M. B.), Ahmedabad
 
Cost of Work : Rs. 4.38 Millions
 
Year of Completion : February 1997
 
 

 
Name of Work : Providing Berthing facilities (RCC) jetty for port crafts at Port Magdalla
 
Client : The C. E. O. & V. C. (G. M. B.), Ahmedabad
 
Cost of Work : Rs. 3.5 Millions
 
Year of Completion : September 1996
 
 

 
Name of Work : Widening of New RCC Jetty for providing additional transit area at port Magdalla, Surat
 
Client : The C. E. O. & V. C. (G. M. B.), Ahmedabad
 
Cost of Work : Rs. 4.83 Millions
 
Year of Completion : April 1996
 
 

 
Name of Work : Widening of Old R.C.C. Jetty for Providing additional Transit area at Port Magdalla, SURAT
 
Client : The C. E. O. & V. C. (G. M. B.), Ahmedabad
 
Cost of Work : Rs. 10.87 Millions
 
Year of Completion : January 1996
 
 

 
Name of Work : Construction of Bored Pile foundation, Pile cap fender skirts, Cast - in - situ fender wall, R.C.C. Precast Beams for EDC Jetty & Fender Pile Replacement Projects for Reliance Industries Limited at Hazira near, SURAT.
Construction of Bored Pile foundation, Pile cap fender skirts, Cast - in - situ fender wall, R.C.C. Precast Beams for EDC Jetty & Fender Pile Replacement Projects for Reliance Industries Limited at Hazira near, SURAT.
 
Client : General Manager ECC Construction Group
C/o. L & T Ltd.
 
Cost of Work : Rs. 7 Millions (excl. cost of material)
 
Year of Completion : April 1995
 
 

 
Name of Work : Extension of R.C.C Jetty at port Magdalla, SURAT.
 
Client : The C. E. O. & V. C. (G. M. B.), Ahmedabad
 
Cost of Work : Rs. 13.9 Millions
 
Year of Completion : December 1994
 
 

 
Name of Work : Extension of fishing Jetty at Vanakbara, DIU
 
Client : The Exe.Engineer P. W. D., DAMAN
 
Cost of Work : Rs. 2 Millions
 
Year of Completion : April 1990
 
 

 
Name of Work : Extension of Fishing Jetty towards Sea side at Nani Daman
 
Client : The Exe. Engineer P. W. D., DAMAN
 
Cost of Work : Rs. 2.15 Millions
 
Year of Completion : February 1990