Name of Work
: |
Construction of Retaining wall for flood Control from kota Barrage to Nayapura Bridge in Kota City. |
|
|
Client : |
UIT Kota. |
|
Cost of Work : |
Rs.3080 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of Bridge across Tapi River and along Varachha Creek near Varachha Main Road and near Varachha water works (4 Lane) at Surat. |
|
|
Client : |
Surat Municipal Corporation. |
|
Cost of Work : |
Rs.1679.9 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of flyover (Bridge) at three Major 4 Arm Junction at 03 Places (Ring Road Junctions, A, B & G) (CH. 10/3, 12/3 & 14/6 KM) on Ring Road/ bypass (DNH) coming in the alignment of newly declared NH 84 8A in UT of Dadra & Nagar Haveli on EPC Mode. |
|
Client : |
PWD Silvassa. |
|
Cost of Work : |
Rs.772.2 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of underpass and other works at Aerodrome Circle Kota, including Beautification(Package-01). |
|
|
Client : |
UIT Kota. |
|
Cost of Work : |
Rs.467.6.9 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of underpass and flyover at Indira Gandhi Chouraha, Gumanpura Kota. |
|
|
Client : |
UIT Kota. |
|
Cost of Work : |
Rs.580 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of Flyover with approach portion and service roads at Dokmardi road junction and lions school junction on EPC mode at silvassa. |
|
Client : |
PWD, WD-II(R), Silvassa. |
|
Cost of Work : |
Rs.803.7 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of c.c. pavement and allied works including footpath, street light & horticulture etc. from Bhesan road canal culvert to SUDA limit under Package-15 A Chainage (4+550 to 6+250). |
|
Client : |
Surat Municipal Corporation , Road Division. |
|
Cost of Work : |
Rs.90 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of High level bridge on Kolak River at Pataliya Causeway on NH848B. |
|
Client : |
PWD Daman. |
|
Cost of Work : |
Rs.107.6 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of Flyover from Danbari to Keshavpura circle on Rangbari road, Kota including development of side service road & slip lane. |
|
|
Client : |
UIT, Kota. |
|
Cost of Work : |
Rs.1400 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of River Bridge Across River Tapi Joining Ved- Variyav, Surat. |
|
|
Client : |
Surat Municipal Corporation, Surat. |
|
Cost of Work : |
Rs.1184.2 Million. |
|
Year of Completion : |
Work in progress |
|
|
|
|
|
Name of Work
: |
Construction of High Level Bridge connecting Dudhani and Kauncha across Damanganga river in U.T. of Dadra and Nagar Haveli (3rd call). |
|
|
Client : |
PWD, Civil Division No. II, Dadra & Nagar haveli, Silvassa. |
|
Cost of Work : |
Rs.547.1 Million. |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of New 4-lane Bridge across Versova Creek and its approaches with Interchange from km 496.100 to km 498.350 (approx. 2.250 km) between Surat-Dahisar section of NH-8 (New NH-48) in the State of Maharashtra on EPC Mode Project. |
|
|
Client : |
National Highway Authority of India, Delhi. |
|
Cost of Work : |
Rs.1574.9 Million (VMC's Scope 1070 Million) |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction for bridge across River Tapi Joining SVNIT Junction - Umara and Pal Village at Surat on (EPC Basis). |
|
|
Client : |
Surat Minicipal Corporation, Surat. |
|
Cost of Work : |
Rs.910 Million |
|
Year of Completion : |
July, 2021 |
|
|
|
|
|
Name of Work
: |
Construction of High level Bridge Parallel to Kota Barrage, Kota. |
|
|
Client : |
UIT Kota. |
|
Cost of Work : |
Rs.526.1 Million |
|
Year of Completion : |
Novermber, 2018 |
|
|
|
|
|
Name of Work
: |
Construction of Major Bridge on River Narmada from Km.469/00 to 470/00 on NH-56 in the State of Gujarat. (Job No. NH-56 / Gujarat (17)/14-S&R(B)-018). |
|
|
Client : |
National Highway Division, Bharuch. |
|
Cost of Work : |
Rs.413.2 Million |
|
Year of Completion : |
September, 2020 |
|
|
|
|
|
Name of Work
: |
Construction of 2 way 2 lane Fly Over Bridge covering Anjali Cross road,Paldi Bhatthaand fathehpura junction including Underspace Development on Ashram Road in Ahmedabad City. |
|
|
Client : |
Ahmedabad Municipal Corporation, Ahmedabad |
|
Cost of Work : |
Rs.878.1 Million. |
|
Year of Completion : |
October, 2019 |
|
|
|
|
|
Name of Work
: |
Construction of Bridge with approaches across Damanganga River connecting Kachigam on Nani daman side and Zari on Moti Daman Side in U.T. of Daman. |
|
|
Client : |
PWD, WD-I, Daman. |
|
Cost of Work : |
Rs.475.4 Millions |
|
Year of Completion : |
Nov, 2018 |
|
|
|
|
|
Name of Work
: |
Construction of Bridge from Magarwada Moti Daman to Kanchigam Nani Daman across river Damanganga (Bridge Portion). |
|
Client : |
OIDC Ltd., Daman. |
|
Cost of Work : |
Rs.496.1 Millions |
|
Year of Completion : |
Jul, 2018 |
|
|
|
|
|
Name of Work
: |
Construction of Bridge over construction of Bridge over River chambal between Makhida (District Bundi) and Gainta (District kota) SH No. 1A. |
|
|
Client : |
PWD, Bridge Project, Bundi. |
|
Cost of Work : |
Rs.831.6 Millions |
|
Year of Completion : |
Nov, 2018 |
|
|
|
|
|
Name of Work
: |
Construction of flyover on Bopal junction along SP Ring road in AUDA area. |
|
|
Client : |
AUDA, Ahmedabad. |
|
Cost of Work : |
Rs.880.6 Millions |
|
Year of Completion : |
July, 2017 |
|
|
|
|
|
Name of Work
: |
Construction of Pedestrian Bridge connecting Nani Daman & Moti Daman across Damanganga River near Old Damanganga Bridge. (2nd Call) |
|
|
Client : |
PWD, WD-I, Daman. |
|
Cost of Work : |
Rs.215 Millions |
|
Year of Completion : |
May, 2017 |
|
|
|
|
|
Name of Work
: |
Construction of Narol Flyover at Km. 6+400 on NH-8, in the state of Gujarat. |
|
Client : |
Modern Road Makers Pvt. Ltd., Mumbai. |
|
Cost of Work : |
|
|
Year of Completion : |
Sep, 2017 |
|
|
|
|
|
Name of Work
: |
Construction of Sharavathi major bridge on NH 17 in Karnataka. |
|
|
Client : |
Modern Road Makers Pvt. Ltd., Mumbai. |
|
Cost of Work : |
Rs.495 Millions |
|
Year of Completion : |
Feb, 2017 |
|
|
|
|
|
Name of Work
: |
Construction of Kollur Major bridge (Design chainage 272+840) on NH 17 in the State of Karnataka. |
|
|
Client : |
Modern Road Makers Pvt. Ltd., Mumbai. |
|
Cost of Work : |
Rs.212.4 Millions |
|
Year of Completion : |
Mar, 2017 |
|
|
|
|
|
Name of Work
: |
Construction of two lane elevated structure on LHS near Marvante Village on NH 17 in the state of Karnataka. |
|
|
Client : |
Modern Road Makers Pvt. Ltd., Mumbai. |
|
Cost of Work : |
Rs.138.1 Millions |
|
Year of Completion : |
Feb, 2017 |
|
|
|
|
|
Name of Work
: |
Construction of Rail Over Bridges at Km. 75+425 & Km. 106+475 of the subject project on NH 8. |
|
Client : |
Modern Road Makers Pvt. Ltd., Mumbai. |
|
Cost of Work : |
Rs.1.72 Millions |
|
Year of Completion : |
|
|
|
|
|
|
Name of Work
: |
Construction of Bridge across river Aghanashini, Karnataka. |
|
|
Client : |
Modern Road Makers Pvt. Ltd., Mumbai. |
|
Cost of Work : |
Rs.102.4 Millions |
|
Year of Completion : |
May, 2017 |
|
|
|
|
|
Name of Work
: |
Construction of Negaria High Level Bridge incl. approach roads on Kekri Deoli Road in Dist. Tonk on EPC basis. |
|
Client : |
RSRDCC Ltd., Deoli, Dist. Tonk. |
|
Cost of Work : |
Rs.498.8 Millions |
|
Year of Completion : |
Nov, 2015 |
|
|
|
|
|
Name of Work
: |
Construction of bridge acroos river Mahi nr. Vasad on NH 8 in state of Gujarat. |
|
Client : |
Modern Road Makers Pvt. Ltd., Mumbai. |
|
Cost of Work : |
|
|
Year of Completion : |
|
|
|
|
|
|
Name of Work
: |
Construction of Bridge in place of Hope Bridge across river Tapi joining Chowk and Adajan, Surat. |
|
Client : |
Surat Municipal Corporation, Surat. |
|
Cost of Work : |
Rs.664.8 Millions |
|
Year of Completion : |
Mar, 2018 |
|
|
|
|
|
Name of Work
: |
Construction of parallel bridge to the existing Diu Ghoghla Bridge across sea creek at Diu. |
|
Client : |
OIDC Ltd., Daman. |
|
Cost of Work : |
Rs.358.7 Millions |
|
Year of Completion : |
July, 2015 |
|
|
|
|
|
Name of Work
: |
Construction of Railway Over Bridge (ROB) in lieu LC No. 3C on Surat – Bhusaval main line and Bhestan – Bhusaval loop line joining Dindoli and Godadara area on 45 m wide T.P. / D. P. road at Surat. |
|
|
Client : |
Surat Municipal Corporation. |
|
Cost of Work : |
Rs.301.7 Million |
|
Year of Completion : |
Work in Progress |
|
|
|
|
|
Name of Work
: |
Construction of Flyover Bridge on Surat Hazira main road near Star Bazar Junction, Surat. |
|
|
Client : |
Surat Municipal Corporation |
|
Cost of Work : |
Rs.277.8 Million |
|
Year of Completion : |
April, 2014 |
|
|
|
|
|
Name of Work
: |
Construction / Widening of Creek bridge near APMC Market on Surat – Bardoli as per 60 m wide road of Draft T.P. Scheme No. 34, Surat. |
|
|
Client : |
Surat Municipal Corporation. |
|
Cost of Work : |
Rs.67.8 Million |
|
Year of Completion : |
December, 2013 |
|
|
|
|
Name of Work
: |
Construction of 2 lane ROB between Bhestan and Sachin at Surat. |
|
|
Client : |
Surat Urban Development Authority. |
|
Cost of Work : |
Rs.166 Million |
|
Year of Completion : |
July 2013 |
|
|
|
|
|
Name of Work
: |
Construction of flyover bridge (six lane) at Sosyo Circle Junction on Udhna – Magdalla Road in Surat City. |
|
|
Client : |
Surat Municipal Corporation. |
|
Cost of Work : |
Rs.267.8 Million |
|
Year of Completion : |
June 2013 |
|
|
|
|
|
Name of Work
: |
Widening of existing creek bridge on Surat – Bardoli road (NH No. 6) as per 60 m T.P. road on T.P. No. 54 (Dumbhal – Magob) near M. D. Landmark Estate in Surat. |
|
|
Client : |
Surat Municipal Corporation. |
|
Cost of Work : |
Rs.34.7 Million |
|
Year of Completion : |
June, 2013 |
|
|
|
|
|
Name of Work
: |
Construction of Surface Level pass on NH-12, Kota. |
|
|
Client : |
Urban Improvement Trust, Kota. |
|
Cost of Work : |
Rs.113 Millions. |
|
Year of Completion : |
May, 2013 |
|
|
|
|
|
Name of Work
: |
Construction of Elevated road on NH-12, Kota. |
|
|
Client : |
Urban Improvement Trust, Kota. |
|
Cost of Work : |
Rs.561 Millions. |
|
Year of Completion : |
February, 2013 |
|
|
|
|
|
Name of Work
: |
Construction of bridge across river Tapi between Kapodara-Utran at Surat. |
|
|
Client : |
Surat Municipal Corporation, Surat. |
|
Cost of Work : |
Rs.750 Millions |
|
Year of Completion : |
May 2012 |
|
|
|
|
|
Name of Work
: |
Construction of bridge across river Ambika, Flyover at Gandeva, Flyover at Alipore and ROB at Bilimora on Surat Dahisar section. |
|
|
Client : |
Modern Road Makers Pvt. Ltd., (IRB), Mumbai. |
|
Cost of Work : |
Rs.184.8 Million (excluding cost of material) |
|
Year of Completion : |
August 2011 |
|
|
|
|
|
Name of Work
: |
Construction of 2 - two lane Flyover bridge on 60 m wide Surat - Bardoli Road at Aai Mata junction for BRTS under JuNURM Scheme, Surat. |
|
|
Client : |
Surat Municipal Corporation, Surat. |
|
Cost of Work : |
Rs.326 Millions. |
|
Year of Completion : |
January 2011 |
|
|
|
|
Name of Work
: |
Design and Construction of ROB on DCM Railway Crossing at Kota, Rajasthan. |
|
|
Client : |
Urban Improvement Trust, Kota |
|
Cost of Work : |
Rs.251.59 Million. |
|
Year of Completion : |
May 2009 |
|
|
|
|
Name of Work
: |
Design and Construction of bridge across Godavari river on Ahmednagar Aurangabad section. |
|
|
Client : |
Keti Sangam Infrastructure (I) Ltd., Indore.
A work of PWD, Mahrashtra. |
|
Cost of Work : |
115.4 Million (Excl. cost of material) |
|
Year of Completion : |
March 2009 |
|
|
|
|
Name of Work
: |
Construction of bridge across river Pravara on Ahmednagar Aurangabad section. |
|
|
Client : |
Keti Sangam Infrastructure (I) Ltd., Bhopal |
|
Cost of Work : |
Rs.33.3 Million (Excl. cost of material) |
|
Year of Completion : |
March 2009 |
|
|
|
|
Name of Work
: |
Construction of Railway bridge across river Narmada near Jabalpur on Gondia Jabalpur gauge conversion project. |
|
|
Client : |
South East Central Railway, Bilaspur. |
|
Cost of Work : |
Rs.345.62 Million. |
|
Year of Completion : |
January 2009 |
|
|